Newtown Creek (35-G) North and North Central Batteries

Major Facets

125,000 cubic yards of concrete construction.

225,000 cubic yards of excavation and disposal of contaminated and hazardous earth material.

Construction includes a new 40,000 sq.-ft. control building.

Installation of eight new process air blowers and interim air blower facility.

Extensive support of excavation, pile foundations, dewatering and mechanical installations.

Installation of 100,000 lf of piping